A leading light aircraft manufacturer based at Santa Monica Airport needed a 10,000 SF hangar remodel that matched the precision of the aircraft they build. Ground-floor showroom, second-floor offices, full A&E services, every crew member vetted for active airfield access. Four months. On time. On budget.
You have a hangar. You have a vision for what it needs to become. You have a brand that does not accept average. And you are trying to find a contractor who can navigate an active airport environment without getting your crew access revoked, your project shut down, or your opening date pushed back six weeks while everyone figures out what they should have planned before they started.
That is exactly the situation a leading light aircraft manufacturer based at Santa Monica Airport was in when they came to Pacific Southern Development. They needed a 10,000 SF hangar transformed into a flagship showroom and operational headquarters, in four months, inside an active airfield where every crew member required individual background screening and credentialing before stepping on site.
Most contractors cannot do this. Not because the construction is beyond them, but because the logistics, the permitting coordination, the crew vetting, and the daily access management across four months of active construction is a level of operational discipline most commercial contractors have never had to develop. Getting it wrong does not just delay the project. It shuts it down.
Every crew member, every subcontractor, every delivery driver entering the secured perimeter of Santa Monica Airport must be individually background-screened and credentialed by the airport authority. A single uncleared person on site is an immediate security violation and work stoppage. Coordinating this across every trade for four months is a logistics challenge most contractors are not equipped to manage.
Projects at Santa Monica Airport do not go through LADBS. They go through the City of Santa Monica's own Building and Safety Department, with additional coordination required through airport management. Missing either layer of this process delays the project. Getting ahead of it from day one is what keeps the schedule intact.
Working inside an active airport is not something you improvise. It requires pre-project planning, complete crew credentialing before groundbreaking, and a project management approach that treats access logistics as seriously as construction sequencing.
We coordinated the complete background screening and airport credentialing process for every crew member across every trade before construction started. Not a single person stepped on the airfield without clearance. Not once across the entire four-month build.
We submitted architecture and engineering documents to the City of Santa Monica and coordinated with airport management from pre-construction so permit review timelines were built into the four-month schedule, not discovered mid-project.
We provided full A&E services and served as general contractor on this project. One team, one contract, one point of accountability from the first drawing to the final inspection. No gaps between design and construction. No finger-pointing when challenges came up.
A hangar remodel for a precision aircraft manufacturer at an active airport is not a project you hand to a contractor without a proven track record in complex commercial environments.
20+ years of commercial construction across the most demanding markets in LA.
Leadership with decades of complex commercial construction management.
Clients cite communication, precision, and on-schedule delivery.
General Contractor B, C-10 Lic #884094. BBB Accredited.
A leading light aircraft manufacturer based at Santa Monica Airport needed to transform their 10,000 SF hangar into a showroom and operational headquarters that reflected the quality and precision of their aircraft. The ground floor was converted into a flagship showroom environment for client presentations and aircraft display. The second floor was built out as a functional office headquarters for the company's operations team.
Pacific Southern Development provided full architectural and engineering services, pulling permits through the City of Santa Monica and coordinating with airport management throughout. The showroom floor was ground, stained, and sealed to the polished finish that a premium aviation brand requires. Showroom lighting was upgraded with an $8,000 allowance to illuminate the aircraft and the space at the level the brand demands. The second floor received new conference rooms including dedicated Debrief A and B rooms, an executive corridor, a full kitchen build-out, and a complete low-voltage upgrade from CAT4 to CAT6 throughout.
Every crew member was individually vetted and credentialed for active airfield access before work began. Not a single access incident occurred across the four-month project. The completed space was delivered on time and on budget, fully permitted and inspected through the City of Santa Monica.
Santa Monica Airport is an active airfield with flight operations running alongside construction. That means every crew member, every subcontractor, and every delivery driver who enters the secured perimeter must be individually background-screened and credentialed by the airport authority before they set foot on site.
One uncleared person on the airfield is not a warning. It is an immediate shutdown. Managing this across a full construction team, multiple trades, and a four-month schedule requires a level of pre-project coordination and daily logistics discipline that most commercial contractors have never had to develop.
Pacific Southern Development coordinated the complete vetting and credentialing process for every crew member across every trade before groundbreaking. Airfield access was tracked and maintained throughout the project. Not a single access incident occurred from start to finish.
A project at an active airport cannot be improvised. Every step, from crew credentialing to permit sequencing to trade coordination, was planned before construction started.
Architecture and engineering completed and submitted to City of Santa Monica. Airport authority coordination initiated. Full crew credentialing process launched across all trades. Every material delivery, trade sequence, and fabrication lead time locked before groundbreaking. Nothing improvised on a fixed four-month timeline.
Demo, framing, HVAC, electrical, low voltage, plumbing, flooring, paint, millwork, and fire alarm sequenced across both floors. Daily airfield access tracked for every crew member. City of Santa Monica inspections coordinated at each phase. Client updated at every milestone.
City of Santa Monica final inspection passed. Full punch list resolved before handoff. The client received a completed aircraft showroom and operational headquarters on the date they planned from day one, with every scope item delivered as specified.
Pacific Southern Development provided architecture, engineering, and general contracting on this project. Every scope item below was delivered under one contract with one team.
Full A&E services provided for permit submission to City of Santa Monica Building and Safety, including all required drawings and engineering calculations.
New sinks and faucets installed in restrooms and kitchen throughout both floors.
10,000 SF. Two floors. Active airport logistics. Dual-jurisdiction permitting. Full A&E services. Every trade coordinated under one contract. Four months. Delivered on time and on budget.
Full hangar remodel across ground floor showroom and second floor offices.
Complete build-out from groundbreaking to handoff in four months.
Full crew vetted and credentialed. Not a single airfield access violation across the project.
"We had every crew member credentialed, permits submitted, and a sequenced construction schedule before anyone touched a single wall. That is not how most contractors operate, and it is exactly why we did not have a single access issue or permit delay across the entire four-month project. The showroom we ended up with reflects the standard we hold our aircraft to. That was the requirement. Pacific Southern Development delivered it."
If you have a project in a restricted environment, a complex jurisdiction, or a space that needs to reflect a brand that does not accept average, here is what the other side of a project like this looks like when the right contractor is running it.
Not the date that kept slipping because permits were not submitted on time, or because a crew member was denied airfield access, or because no one sequenced the trades before groundbreaking. The date you put on the calendar before the contract was signed. That is what planning looks like when it is done correctly.
The showroom floor is polished. The lighting makes the aircraft look the way it was designed to look. The second floor operates the way your team needs it to operate. Every detail reflects the standard your brand holds for everything it builds. That is what the client in this case study walked into.
No chasing permits. No tracking crew credentials. No calling the inspector to reschedule. No wondering what is happening on site between updates. One contractor, one contract, one team that handled every moving part from the first drawing to the day you walked in and the space was ready. That is what working with the right contractor actually feels like.





Full-scope commercial construction throughout Los Angeles, from standard tenant improvements to complex multi-trade build-outs in restricted environments.
Learn More →Tenant improvements coordinated with landlords, architects, property managers, and permitting jurisdictions throughout the greater Los Angeles area.
Learn More →Commercial construction and remodeling in Santa Monica with full City of Santa Monica permitting experience and airport authority coordination.
Learn More →